Line-by-line build-up

Materials = supply cost; labour = what the trade charges for that element; fees & prelims = design, Building Control, party wall, scaffold, skips and site costs. Ranges are typical 2026 UK figures outside London. Every line links to the guide that explains it; labour figures assume the day rates in the Cost Index.

ElementMaterialsLabourFees & prelimsNotes
Design, planning application, calcs & Building Controlindex ↗ – – £5,300–£8,600 Full planning usually required; architect at 8–15% of build
Party wallindex ↗ – – £1,250–£2,850 Two-storey work on a shared wall, often two surveyors
Scaffoldingindex ↗ – – £2,200–£3,250
Excavation, deeper foundations & drainageindex ↗ £2,750–£4,000 £5,150–£7,500 – Foundations sized for two storeys
Floor slab & screedindex ↗ £1,600–£2,150 £2,200–£3,000 –
Cavity walls, two storeys £5,850–£8,300 £10,850–£15,400 –
Steels (ground-floor opening + first-floor support)index ↗ £1,450–£2,300 £2,350–£3,800 –
First-floor joists & deck £1,100–£1,600 £2,400–£3,400 –
Pitched roof (tiles to match) & rainwaterindex ↗ £3,000–£4,200 £4,900–£6,900 –
Windows (first floor) & bifolds/doors (ground)index ↗ £3,900–£7,000 £1,550–£2,700 –
Electrics, both floorsindex ↗ £800–£1,150 £2,900–£4,050 –
Plumbing, heating & new bathroomindex ↗ £2,000–£3,100 £4,200–£6,550 – Incl. mid-range bathroom suite & tiling
Insulation & plastering, both floorsindex ↗ £2,300–£3,150 £3,400–£4,750 –
Flooring, doors, decorationindex ↗ £2,100–£3,300 £3,200–£4,950 –
Skips & site costsindex ↗ – – £1,300–£2,150
Sub-totals (34% / 53% / 13%)£26,850–£40,250£43,100–£63,000£10,050–£16,850
Build-up total£80,000–£120,100vs published guide range £80,000–£120,000

The published guide for this job quotes £80,000–£120,000, which is the figure the build-up above is reconciled against.

Common additions & variations

How to use this

Treat the build-up as a sanity check on quotes, not a price list: a builder's quote that lands inside the total range with a similar materials/labour split is priced normally; one far below it is usually missing scope. Get three itemised quotes, compare them line by line against this table, and ask about anything that's absent. Figures exclude VAT where the trade is VAT-registered (most are above ~£90k turnover), and exclude fees you pay directly such as planning application fees.

Other build-ups