The JCT publishes the contracts the UK construction industry runs on, and two of them are written deliberately for homeowners, in plain English, short enough to read over a coffee. If your builder “doesn’t really do contracts”, the Home Owner Contract is the answer that removes every excuse: it’s cheap, it’s fair to both sides, and builders who refuse it are telling you something.

The two versions

HO/B, Building Contract for a Home Owner/Occupier who has not appointed a consultant. You deal with the builder directly: you define the work, the builder prices it, the contract records it.1 This is the version for most renovations, bathrooms, garden buildings and smaller extensions where no architect is administering the job.

HO/C, Building Contract for a Home Owner/Occupier who has appointed a consultant. The same shape, but a named consultant (architect, surveyor or project manager) oversees the works, checks quality and values payments. It pairs with a separate JCT Consultancy Agreement for appointing that consultant.2 Use it when your architect is running the contract on site.

Both are sold through the JCT online store, as a hardcopy or a digital fill-in: £40 plus VAT for HO/B and £46 plus VAT for the HO/C pack, which includes the consultancy agreement.31 There is no licence issue with using them, that’s what they’re for.

What the contract pins down

The form is short but covers the points most disputes grow from:

  • The work, described by reference to your drawings, specification or a written list, all attached
  • The price, fixed, with VAT shown, and a stated list of anything provisional1
  • Payment, either a single payment on completion or stage payments you fill in; there is no automatic right to a deposit1
  • Timing, start and finish dates, working hours, and how the date moves for genuine delay
  • The site, access, toilets, storage, and who insures what while work is under way (the builder carries injury and damage liability; you notify your home insurer)
  • Changes, instructions must be priced, and you can ask for a written quote before deciding
  • Finishing, the builder must correct defects that appear within three months of completion, at no cost
  • Fallout, a built-in disputes clause including adjudication, so there is a private, quick route to a binding decision without court1

Minor Works also defaults to a three-month rectification period unless the parties agree otherwise, so if you want a longer window, such as six or twelve months, write it into the contract.4

Home Owner vs Minor Works

Home Owner (HO/B, HO/C)Minor Works (MW)
Written forDomestic clientsIndustry users
Typical job sizeSmall domestic worksSimple projects, often larger
Length / languageShort, plain EnglishLonger, technical
Defects period3 months3 months unless agreed otherwise
Contract administratorOptional (HO/C)Assumed
Liquidated damagesNo, general damages onlyYes, weekly figure

If your project has structural work, a long programme, or you want a fixed weekly figure for late completion, the Minor Works form is worth its extra complexity, our builder contracts guide covers it clause by clause.4 For everything smaller, the Home Owner form beats a builder’s one-page “terms” comfortably, mostly because it was drafted to be fair rather than to protect one side.

Filling it in without a solicitor

You don’t need one. The traps to avoid are practical, not legal:

  1. Attach the documents. The contract is only as good as the drawings and specification it references. “Work as discussed” defeats the point.
  2. List provisional sums honestly. Anything not yet designed (the kitchen, the landscaping) should carry a stated allowance, so the final account holds no ambushes.
  3. Fill in the payment schedule. Stages tied to milestones, not dates, and always slightly behind the value of work done.
  4. Both parties sign both copies before work starts, not during week two.

The bottom line

For the price of a takeaway you convert a handshake into enforceable rights, over price, programme, defects and disputes. Pair it with sensible vetting and the payment discipline in our contracts pillar, and you’ve removed the conditions most disputes need to grow.

This guide is general information for homeowners in England and Wales, not legal advice.

References (4)

Figures in this note were checked against the sources below on 30 September 2026. Superscript numbers in the text point to them. Every source the site cites, by topic.

  1. 1technicalstrongThe Joint Contracts Tribunal, guidance.RN-267X3CJCT's product page for its homeowner building contract. It says the contract is for a homeowner dealing directly with the contractor and suits small domestic work such as extensions.
  2. 2technicalstrongJCT, guidance.RN-BJ7DMOJCT announcement of the 2021 Home Owner contracts: HO/B, and HO/C sold together with the HO/CA consultancy agreement.
  3. 3costgoodThe Joint Contracts Tribunal, a page from the body itself.RN-D2653HA price, true at 2026-09. The publisher's own product page for the JCT Home Owner contract variant intended for a home owner or occupier who has appointed a consultant to administer the contract on their behalf, which is the HO/C form as distinct from HO/B where the homeowner deals with the builder directly. It sits in JCT's Home Owner Contracts category, the suite JCT publishes specifically for domestic building work rather than commercial projects. Use this to confirm which JCT home owner form applies when a note tells a reader to put the job on a written standard contract.
  4. 4technicalstrongJCT, guidance.RN-FVA7R0JCT guidance notes to the Minor Works contract, defining the default three-month rectification period and the liquidated damages remedy for late completion.
  1. Building Contract for a Home Owner/Occupier who has not appointed a consultant to oversee the work (HO/B) 2021, JCT, accessed 30 September 2026. jctltd.co.uk

  2. JCT Home Owner Contracts 2021 Edition launched, JCT, accessed 30 September 2026. corporate.jctltd.co.uk

  3. Building Contract and Consultancy Agreement for a Home Owner/Occupier (HO/C and HO/CA) 2021, JCT, accessed 30 September 2026. Priced at 2026-09 and left there. jctltd.co.uk

  4. Minor Works Building Contract 2011: Guidance Notes, JCT, accessed 30 September 2026. jctltd.co.uk